Decommissioning Dev Clusters¶
We had more development and QA environments than teams to use them: 13 Kubernetes clusters, each split into shards, and each costing thousands a month. I led the work to retire the ones nobody needed, together with the platform and SRE teams. Removals had been waiting on a platform team that couldn't keep pace, so my team took the work on.
The outcome: 8 of the 13 clusters retired. Spend on those clusters fell by more than 99% within three months, and the GitOps controller had about 1,000 fewer applications to manage, which improved its performance for every other team.
Creating a cluster is a well-trodden path. Removing one isn't. These clusters had been built at different times by different methods, so the process had to be worked out and written down as we went. This page is that process, condensed.
1. Choose with evidence¶
Proposing to remove a development environment gets pushback, and fair enough: nobody wants their environment to vanish. Evidence turns that into a conversation about facts. For each candidate cluster we built a scorecard:
| Signal | Where it came from | What it tells you |
|---|---|---|
| Cost | Daily cost filtered by the cluster tag, with a projection for next month | What keeping it costs |
| Usage | Login snapshots from every shard, restored side by side | Unique logins per day, and how many teams were still using each cluster |
| Health | Error counts and pod churn from daily log queries over four weeks, compared with a baseline | Whether it's healthy, or quietly broken and ignored |
| Data size | Snapshot sizes | How much real work lives there |
| Version drift | Product versions running on each cluster, compared with the latest release | How far behind it was, and whether anyone was still deploying to it |
| Owners | Polls and direct questions | What the data can't say |
The usage analysis never touched the clusters. Snapshots were restored into local containers and queried there, so it needed no cluster access and put no load on anything still in use.
The first batch was chosen from polls, activity checks and a shared spreadsheet. As the obvious candidates ran out, I turned the scorecard into a small CLI that produced all four reports for any list of clusters, so any review could be rerun on demand.
The scorecard also told us when to stop. Once the remaining clusters were genuinely in use, decommissioning paused, and the tooling stayed ready for the next review.
Somewhere to go¶
Retiring shared clusters only works if teams have somewhere else to work. In parallel, we were moving teams to local Kubernetes development with Tilt: services ran and were tested on the developer's own machine, and we tracked adoption across repositories to see which teams had moved. Every team that moved needed a shared cluster a little less. For a hands-on example of local Kubernetes with Tilt, see Implementing Observability with Prometheus, VictoriaMetrics, and Tilt.
2. Announce¶
Before anything changed, the owning teams got a notice with a date and a plain list of what would go: buckets, volumes and instances, each with what to back up. Nobody should find out by losing access.
3. Wind down¶
The first technical step was to power the nodes down, not delete anything. Cost drops straight away, and anyone who still needs the cluster finds out while it can still be brought back. The silence that follows is the final confirmation.
4. Tear down in order¶
Teardown runs top down, and each step has one owning team. Every change of lane in the diagram is a handoff, and the next team doesn't start until the step before is done. The runbook was written with the SRE and platform engineers, and signed off by the platform team.
Finalizers come first. Applications are removed through GitOps (Argo CD), and finalizers make that deletion cascade to the stateful sets and volume claims underneath. Without them, deleting an application leaves its storage behind. A short script listed every application on the cluster and reported which ones were missing finalizers, so they could be added before anything was deleted.
Infrastructure goes through review. The cluster itself was destroyed with Terraform through pull requests, using Atlantis: the plan is posted on the PR, reviewed and approved, and only then applied. The first change for each cluster was to its Atlantis project config, so the removal started as a reviewed PR like any other. Removing a cluster is as visible as creating one.
Gotchas¶
Teardown never went exactly to plan. Each of these went into the runbook the first time it bit.
Buckets were the long pole. Deleting the objects in a versioned bucket only adds delete markers, so the old versions stay and the bucket can't be removed. A lifecycle rule to expire them works, but it runs in the background and in its own time, so we waited, checked and came back. It was the most manual part of the process. Start bucket expiry as early as the agreed date allows, so it isn't the last thing holding a cluster open.
5. Prove it's gone, and report¶
A cluster isn't decommissioned when the destroy finishes. It's decommissioned when nothing it owned is still being billed. Each cluster was tracked to a clean finish:
- a sweep for orphaned resources (unattached volumes, idle load balancers, leftover clusters), each with an estimated monthly cost;
- cost by cluster tag, watched until it reached zero;
- a cleanup record per cluster, so every leftover had an owner and a date.
The reported figure was the drop in spend on the retired clusters, month by month.
Looking back¶
- Build the scorecard first. The early picks relied on polls and spreadsheets. The tooling came later, and would have made the first round faster and easier to defend.
- Require finalizers when apps are created, not as a check at teardown. A missing finalizer is cheap to add on day one and expensive to discover on the last day.
- Write the runbook as you go. Every cluster taught us something. Writing it down each time is what made the next one quicker and more complete.